The demolition of the Puskás Ferenc Stadium will last for 8 months

Change language:
Origo.hu writes that, according to the plans, the demolition works of the Puskás Ferenc Stadium that already started will last for 8 months. The construction of the new arena can start this December and it will be finished in 2019.
According to the National Sport Centres, they are currently changing the public utilities and doing value saving works, while the demolition of the big ferro-concrete skeleton will probably start in the second part of March.
There is 50 thousand cubic metre concrete and ferro-concrete waiting to be demolished in the stadium. You could fill up 13 swimming pools with this amount of concrete. Moreover, they will move around 170 thousand cubic metre soil during the construction. Out of this, 40 thousand cubic metres will be restored during the construction, 60 thousand cubic metres will be recycled somewhere else and 70 thousand cubic metres will be transferred to a dumpsite.

Legendary moments
The announcement reminds us that the condition of the stadium, which was inaugurated in 1953, significantly worsened in the past decades. The six decades of the stadium contained many unforgettable moments. One of these moments was the legendary win of long-distance runner József Kovács, “Bütyök”, in 1953, over the later Olympic Champion Vladimir Kuc. In the next year, he was the first to defeat the Czechoslovakian long-distance runner Emil Zatopeke at 10 thousand metres, in the world.
This is where the Hungarian Golden Team defeated the English by 7-1 in 1954, on the rematch of the legendary 6-3. They also held European Athletics Championships, European Basketball Championships and women’s football matches in the stadium.
63-70 thousand sitting and standing space
The demolition is in process and the National Sport Centres emphasized that the old stadium – similarly to Groupama Arena – will live on in the new building as a significant part of the scraps will be recycled and rebuilt into the new stadium. The new arena will be up to the most modern sport institutions of the world, the tower building will be elemental in the renewed building, but the once typical masts will also be present in an updated form.